Comment by jpleger

3 months ago

Makes me remember some of the days I had in my career. There were a couple really interesting datacenter things I learned by having to deploy tens of thousands of servers in the 2003-2010 timeframe.

Cable management and standardization was extremely important (like you couldn't get by with shitty practices). At one place where we were deploying hundreds of servers per week, we had a menu of what ops people could choose if the server was different than one of the major clusters. We essentially had 2 chassis options, big disk servers which were 2u or 1u pizza boxes. You then could select 9/36/146gb SCSI drives. Everything was dual processor with the same processors and we basically had the bottom of the rack with about 10x 2u boxes and then the rest was filled with 20 or more 1u boxes.

If I remember correctly we had gotten such an awesome deal on the price for power, because we used facility racks in the cage or something, since I think they threw in the first 2x 30 amp (240v) circuits for free when you used their racks. IIRC we had a 10 year deal on that and there was no metering on them, so we just packed each rack as much as we could. We would put 2x 30s on one side and 2x 20s on another side. I have to think that the DC was barely breaking even because of how much heat we put out and power consumption. Maybe they were making up for it in connection / peering fees.

I can't remember the details, will have to check with one of my friends that worked there around that time.