No regular residential building is set up to host a datacenter off the bat. Even racking more than half a dozen boxes in a given room requires an upgrade.

Most rooms in North America won't be wired for anything over 2.5 kW by default (kitchens and laundry rooms being obvious exceptions).

An electric dryer might pull 5 kW. An electric range ballpark 10 kW. Versus 15 kW per full rack for a fairly tame setup.

And then you've got the problem of dissipating all that heat.