UK power grid has the Eastenders effect. Where the ending credits of the Eastenders soap signals a large increase in power draw from the grid as people will put on the tea kettle at the end of the show. The grid operators have to dispatch enough power to cover for this.
While the amount of energy used to boil water at 2kW is not significantly different from 3kW (2kW has a tiny amount of more atmospheric losses I think), there is a difference for the impact on the grid. Same energy but more power generating and transmission line capacity needed.
Here's a video showing an engineer at the national grid bringing hydro-electric plants online at the closing credits of a popular soap opera in anticipation of the millions of kettle that are about to be switched on!
https://www.youtube.com/watch?v=slDAvewWfrA